SPECIAL RELEASE MARCH 2024

The SVA Roof Project is currently underway, and we humbly request your sacrificial contribution to support the estimated $3K roof endeavor. Your generosity will ensure that the children have a safe and conducive learning environment, especially during the rainy season (200” in 6 months). Your contribution will help us provide the necessary infrastructure for the children’s education.

2024:  The SVA Roofing is Project #1.  The plan for the SVA Bathroom Project #2, including both building and electrical designs, is now in place. We are reaching out to you for your support as we aim to provide every child with a healthy life and improved education at Slakpawein Village Academy. Your contribution towards this project will greatly enhance the development of our academy and ensure a brighter future for all the children in our community. Thank you for your generosity and support. https://gofund.me/6f4b7dc0

PROJECT  # 1:  ROOF

Slakpawein Village Academy Roofing (Phase 2 & 3), March 2024
DescriptionQuantityUnit PriceUS$
zinc11 bundles1251375
cummings15 pcs690
wire nails4 boxes2080
zinc nails8 boxes540
roofing tape4 rolls1040
roofing delt3 rolls1545
Planks (2x2x14)29 pcs1.5646
Planks (2x4x14)14 pcs3.1184
Materials Sub-total: 1800
Transportation 110
Workmanship 490
TOTAL: 2400
Team of 5; 5 working days to complete roof.

PROJECT # 2:  BATHROOM (5 toilet rooms, 1 male urinal room and 2 shower rooms).

There’s an urgent need for the kids’ bathroom estimated at US$3K.  Building materials listing is provided as per your request.